Newbold Road Project Update: Bridge Replacement

◄ Back
February 8, 2017 11:52 AM

Newbold Road Bridge Replacement Project Update

The contractor plans to begin construction on Monday February 20th. Construction is expected to last approximately 3 months. The road will remain open to all traffic during construction.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

June 13, 2017 6:41 AM

The project is near completion and the contractor plans to place seed, mulch, and additional erosion control devices today. The project should be done this week.

Thank you for your cooperation throughout the project. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
May 25, 2017 8:44 AM

The contractor is now building the new road to match into the new bridge. They plan to have the new road open by Friday May 26th. Once the new road is open the original road will be closed off to all traffic.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

March 17, 2017 2:00 PM

The contractor continues to work on the proposed bridge. Newbold Road will remain open to traffic as expected. The contractor plans for an approximate completion date of June 1st.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)