Alice Road Project Update

This project was let on March 21, 2017 and was awarded to L.L. Pelling out of North Liberty. The contract amount is for $983,174. The contractor plans to start construction on Monday, April 24th. Through traffic will be maintained throughout construction, but traffic should expect delays. Traffic will be controlled with flaggers and a pilot car. Construction is expected to take 4-5 weeks to complete.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

June 1, 2017 11:25 AM

Construction on Alice Road is complete. There are a few minor items the contractor needs to clean up, but these should not have an affect on traffic. In the next few weeks Linn County crews will be onsite to start working on driveway culvert extensions.

Thanks for your cooperation throughout the project. Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
May 25, 2017 8:42 AM

The contractor will start painting the pavement markings this morning. This work is expected to take 2-3 days, weather permitting. If you removed your mailbox you can now reinstall it.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

May 17, 2017 7:58 AM

The contractor has completed all the intersections and driveway fillets. They will be finishing the trail crossing later this week and starting on rock shoulders, weather permitting.

With good weather the project should be competed sometime next week. Please contact me with any questions. Thanks for your cooperation.