80th St Project Update: Beverly Road to Highway 30

◄ Back
April 12, 2017 11:02 AM

80th Street SW Project Upate

The project was let on March 28, 2017 and the contract has been awarded to Horsfield Construction, Inc. of Epworth, IA for a cost of $479,102.46. A schedule has not been submitted by the Contractor to date. As per the contract, the late start date for the project is August 28, 2017. The project will take approximately 4-5 weeks for completion.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

June 23, 2017 9:05 PM

The contractor plans to start paving on Monday (26th), weather permitting. They will start on the north end of the project near Highway 30 and pave to the south. They will progress approximately 1/2 mile each day. Paving should only take a total of 2 days. As a reminder, once paving passes by your entrance you will not have vehicle access for approximately 48 hours. Access will be restored once maturity is reached.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
June 20, 2017 11:21 AM

There has been another change in the contractor's schedule. They now plan to start paving on Monday (26th). The paving is expected to take place Monday and Tuesday next week. The contractor changed the schedule because of the potential for rain later this week. Again, sorry for any inconvenience this may have caused.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

June 16, 2017 2:49 PM

There has been a change in the contractor's schedule. They now plan to start paving on Wednesday (21st). The paving is expected to take place Wednesday and Thursday next week.

Sorry for any inconvenience this may have caused. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)