Central City Rd Project: Marion Rd to Fairgrounds

◄ Back
April 12, 2017 11:10 AM

Central City Road Project Update

The project was let on February 28, 2017 and the contract has been awarded to Eastern Iowa Excavating & Concrete LLC of Cascade, IA for a cost of $132,834.97.
As per the contract, the contractor is required to complete the project by June 9, 2017 prior to the 2017 Linn County Fair. No start date has been submitted by the contractor to date.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

June 13, 2017 6:30 AM

The remaining asphalt was placed yesterday. The contractor has some minor shouldering to address then the project will be completed.

Thank you for your cooperation throughout this project. Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
June 7, 2017 2:14 PM

The remaining work is to place asphalt up to the railroad tracks which requires coordination with the railroad. The final lift of asphalt was originally scheduled to be completed today (7th), however, the work was rescheduled for Monday (12th). Once the asphalt is placed the project will be complete.

Please contact me if you have any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org

June 1, 2017 11:32 AM

The contractor has been off site for a few days. The remaining work is to place asphalt up to the railroad tracks which requires coordination with the railroad. The final lift of asphalt is scheduled to be completed on Wednesday (7th).

Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)