Central City Rd Project: Marion Rd to Fairgrounds

◄ Back
April 12, 2017 11:10 AM

Central City Road Project Update

The project was let on February 28, 2017 and the contract has been awarded to Eastern Iowa Excavating & Concrete LLC of Cascade, IA for a cost of $132,834.97.
As per the contract, the contractor is required to complete the project by June 9, 2017 prior to the 2017 Linn County Fair. No start date has been submitted by the contractor to date.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

May 12, 2017 6:52 AM

The contractor will be paving today on the east side of the railroad tracks. The contractor notified us late yesterday of the schedule so I apologize for the short notice. Please contact me with any questions. Thanks for your cooperation. Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
May 12, 2017 6:51 AM

The contractor will be paving today on the east side of the railroad tracks. The contractor notified us late yesterday of the schedule so I apologize for the short notice.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

May 10, 2017 7:16 AM

The contractor has cancelled paving today due to potential rain. They will not pave tomorrow (11th) due to another conflict. I will send out an update as soon as I know when paving is rescheduled.

Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)