Cimarron Drive Project Updates

◄ Back
April 12, 2017 11:17 AM

Cimarron Drive Project Update

The project was let on March 14, 2017 and the contract has been awarded to Hansen Asphalt of Iowa City, IA for a cost of $117,752.00. The contractor has not yet provided a start date, but the contract specifies a late start date of August 29th.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

May 25, 2017 10:20 AM

The contractor plans to start construction on Cimarron Drive on Tuesday May 30th, weather permitting. If the weather cooperates the project should last 4-5 days.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

May 22, 2017 8:31 AM

Due to forecasted rain this week the contractor does not plan to start on Cimarron Drive as originally planned. Once a start date has been reschedule I will send out another update.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 10, 2017 7:22 AM

The contractor has provided a tentative start date of Monday May 22nd. Construction is expected to last 4-5 days, weather permitting.

The contractor will maintain traffic at all times on Cimarron Drive, but delays should be expected. The contractor will be closing Cimarron Court during the paving process during the day.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)