N Center Point Road Project Update

Culvert work and an 8" concrete overlay from County Home Road to the City of Center Point.

Facebook Twitter Google Plus Email

Latest Update:

June 28, 2017 3:11 PM

The contractor has provided a tentative start date of August 14, 2017. More details will be provided once construction nears.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

June 1, 2017 1:38 PM

The project was let on May 23, 2017 and the contract has been awarded to Croell, Inc. of New Hampton, IA for a cost of $4,570,897.88. The project consists of culvert work and an 8” concrete overlay from County Home Road to the City of Center Point. A schedule has not been submitted by the Contractor to date. As per the contract, the late start date for the project is August 14, 2017. The project will take approximately 8-10 weeks for completion.