Buffalo Ridge Road: County Line to Buffalo Creek

◄ Back
June 1, 2017 1:44 PM

Buffalo Ridge Road Project Update

The project was let on May 23, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $1,167,562.94. The project consists of a 3.5” asphalt overlay from the Linn-Jones county line to the bridge over Buffalo Creek just south of McNamara Road. A schedule has not been submitted by the Contractor to date. As per the contract, the late start date for the project is August 28, 2017. The project will take approximately 4-6 weeks for completion.

Facebook Twitter Google Plus Email

Latest Update:

August 16, 2017 10:03 AM

The contractor started paving yesterday and they stopped between Maxwell Road and Burlingham Road. The have resumed paving again this morning. The road will remain open to traffic with the use of flaggers and a pilot car. Even though the road is open delays should be expected.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
August 11, 2017 9:35 AM

The contractor did not start this week as originally planned. They now plan to start on Monday August 14th. Traffic will remain open throughout the project with the use of flaggers and a pilot car. Although access will be available delays are to be expected.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

July 31, 2017 12:56 PM

The contractor has updated their schedule and they now plan to start paving Buffalo Ridge Road early next week (August 7-9th). I will provide a more specific start date when the contractor notifies me.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)