July 7, 2017 2:30 PM

E. Main Street Project Update

The project was let on June 27, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $233,466.40. The contractor has provided a tentative start date of September 4, 2017 and the project should take approximately 3-4 weeks to complete.

Traffic will be maintained throughout the project with the use of a pilot car and flaggers. Although access will be available, delays are to be expected.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

August 2, 2017 11:05 AM

The contractor is paving today and they expect to complete paving tomorrow. After paving they will paint the pavement markings.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
July 31, 2017 12:52 PM

The contractor will be onsite today (31st) doing prep work. They plan to start paving tomorrow (1st). Paving is expected to take approximately 2 days. The road will remain open and traffic will be control with flaggers.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

July 14, 2017 12:27 PM

The contractor has changed their schedule. They now plan to start on Thursday July 20th. They will begin by removing pavement at the Amelia Drive intersection and the east entrance to Westfield Elementary School. Access to Amelia Drive will remain open at all times during construction. The contractor plans to start placing asphalt the first week in August (31st - 4th).

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)