Morris Hills Road Project Update:

The project was let on June 27, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $299,884.00. The contractor has provided a tentative start date of July 20, 2017 and the project should take approximately 2-3 weeks to complete.

Traffic will be maintained throughout the project with the use of a pilot car and flaggers. Although access will be available, delays are to be expected.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

July 31, 2017 12:50 PM

The paving is complete and the contractor is shouldering today. The project is expected to be completed early this week.