◄ Back
August 11, 2017 10:13 AM

Covington Road Project Update:

The project was let on July 11, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $1,197,379.15. The contractor tentatively plans to start the week of August 28th and the project should take approximately 5-6 weeks to complete. Traffic will remain open with the use of flaggers and a pilot car. Although the road will remain open delays should be expected.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

November 3, 2017 8:35 AM

A hyperlink to the project survey is below.

Project Survey

Prior Updates

View All Updates
November 3, 2017 8:24 AM

Thank you for subscribing to receive updates for the asphalt overlay on Covington Road. To continually improve customer satisfaction, we ask that you please fill out the survey at the link below.

https://www.surveymonkey.com/r/PFBVPZX

Thank you for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)

September 19, 2017 8:26 AM

The contractor plans to complete the asphalt work today (19th). They expected to start placing rock shoulders tomorrow (20th) and paint the pavement markings once the shoulders are complete. Construction should be completed in approximately 2 more weeks.

Garret Reddish (garret.reddish@linncounty.org)