East Main Street (near Lisbon)

◄ Back
August 23, 2017 8:15 PM

E Main Street (Lisbon) Project Update

The contractor has provided a tentative start date of Monday September 18th. They will start with a culvert replacement between address numbers 919 and 1000. Once the culvert replacement is complete they will begin the 3.5" asphalt overlay. The road will be closed to through traffic during the culvert replacement and at times during the asphalt overlay. The project is expected to last 4-6 weeks.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Facebook Twitter Google Plus Email

Latest Update:

September 19, 2017 8:19 AM

The contractor plans to start on the culvert replacement this week. The road will be closed just east of house number 919 for 2-3 days. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

September 8, 2017 6:05 AM

The contractor has placed the base lifts of asphalt on the road. Next week, they plan to replace the culvert east of house number 919. The road will be closed at this location for 2-3 days.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)