Sawyer Road Bridge Replacement

◄ Back
November 22, 2017 12:49 PM

Sawyer Road Bridge Project:

The project for a 40'x100' continuous concrete slab bridge was let on November 21, 2017. The contract was awarded to Jim Schroeder Construction, Inc. of Bellevue, Iowa for a cost of $540,927.93. A schedule has not been submitted by the Contractor to date. The project will take approximately 4 months to complete.

Facebook Twitter Google Plus Email

Latest Update:

May 14, 2018 7:39 AM

The project is progressing on schedule and is expected to be completed in early July. Sawyer Road will remain closed to all traffic at the bridge location.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
April 23, 2018 7:06 AM

The bridge replacement project on Sawyer Road is underway. The project is expected to take approximately 3 months and will be completed in July. Sawyer Road will be closed to all traffic at the bridge location.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

April 12, 2018 8:51 AM

Sawyer Road is scheduled to be closed on Tuesday April 17th for the bridge replacement project. The project is expected to last 3 months.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)