Shellsburg Road & Blairs Ferry Road Paving Project

◄ Back
June 4, 2018 8:24 AM

Shellsburg Rd & Blairs Ferry Rd Project Update

The concrete paving project on Shellsburg Road and Blairs Ferry Road will be let on June 12, 2018. Construction includes concrete paving over the existing surface with granular shoulders. A construction schedule has not been determined yet, but is expected to be completed in the Fall of 2018. Additional details will be available after the contract has been awarded.

Facebook Twitter Google Plus Email

Latest Update:

August 17, 2018 6:52 AM

The contractor still plans to start on Monday August 20th. Now, they plan to close Hollenbeck Road and Blairs Ferry Road on Monday. Also, traffic control will be set up on Shellsburg Road, but it will remain open to traffic.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
August 14, 2018 8:11 AM

The contractor still plans to start on Monday August 20th. They will start with a culvert replacement on Hollenbeck Road. Therefore, Hollenbeck Road will be closed on Monday (20th). Work on Blairs Ferry Road and Shellsburg Road will follow very soon.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

August 7, 2018 1:20 PM

The contractor plans to start on Monday August 20th and complete the project by Tuesday November 13th. This schedule is tentative and weather dependent.

Let me know if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)