Buffalo Ridge Road: County Line to Buffalo Creek

1 Alert
June 1, 2017 1:44 PM

Buffalo Ridge Road Project Update

The project was let on May 23, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $1,167,562.94. The project consists of a 3.5” asphalt overlay from the Linn-Jones county line to the bridge over Buffalo...

Read On...

Latest Update:

August 28, 2017 9:45 PM

The contractor has finished paving the mainline road. They are now placing fillets at entrances and paving at intersections. Road shoulders will also be placed.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

County Home Rd Culvert & Grading Update

1 Alert
April 5, 2016 12:03 PM

County Home Road Culverts & Grading Project Update

Road construction on County Home Road between N. Center Point Road and Highway 13 is expected to start the summer or fall of 2017. The project will consist of culvert replacements and ditch grading. County Home Road will remain open to traffic for a...

Read On...

Latest Update:

September 22, 2017 3:53 PM

As a reminder, the contractor plans to close County Home Road between C Ave Ext and Gillmore Road on Monday September 25th. The closure is scheduled for 8:30 AM. A detour will be posted for this closure.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Covington Road: Rogers Rd to Benton County

1 Alert
August 11, 2017 10:13 AM

Covington Road Project Update:

The project was let on July 11, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $1,197,379.15. The contractor tentatively plans to start the week of August 28th and the project should take approximately...

Read On...

Latest Update:

September 19, 2017 8:26 AM

The contractor plans to complete the asphalt work today (19th). They expected to start placing rock shoulders tomorrow (20th) and paint the pavement markings once the shoulders are complete. Construction should be completed in approximately 2 more weeks.

Garret Reddish (garret.reddish@linncounty.org)

East Main Street (Cedar Rapids)

1 Alert
July 7, 2017 2:30 PM

E. Main Street Project Update

The project was let on June 27, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $233,466.40. The contractor has provided a tentative start date of September 4, 2017 and the project should take...

Read On...

Latest Update:

August 2, 2017 11:05 AM

The contractor is paving today and they expect to complete paving tomorrow. After paving they will paint the pavement markings.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

East Main Street (near Lisbon)

1 Alert
August 23, 2017 8:15 PM

E Main Street (Lisbon) Project Update

The contractor has provided a tentative start date of Monday September 18th. They will start with a culvert replacement between address numbers 919 and 1000. Once the culvert replacement is complete they will begin the 3.5" asphalt overlay. The road...

Read On...

Latest Update:

September 19, 2017 8:19 AM

The contractor plans to start on the culvert replacement this week. The road will be closed just east of house number 919 for 2-3 days. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Edgewood Rd Project: Tower Terrace to Toddville Rd

1 Alert
June 1, 2017 1:35 PM

Edgewood Road Project Update

Culvert and grading project from a point a half mile north of Tower Terrace Road to County Home Road.

Latest Update:

September 19, 2017 8:23 AM

The contractor is still working on culvert replacements and grading work. Access is expected to remain open to the north (County Home Road) for the remainder of the project. Dust control has been applied to the rock section near Timber Ridge Trail. Although the dust control will not eliminate all the dust it will greatly reduce it. Once construction is complete Linn County crews will seal coat the rock. It will not remain rock through the winter.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Morris Hills Road: Wickiup LC to Feather Ridge Rd

1 Alert
July 7, 2017 2:33 PM

Morris Hills Road Project Update:

The project was let on June 27, 2017 and the contract has been awarded to L.L. Pelling Co., Inc. of North Liberty, IA for a cost of $299,884.00. The contractor has provided a tentative start date of July 20, 2017 and the project should take approximately...

Read On...

Latest Update:

July 31, 2017 12:50 PM

The paving is complete and the contractor is shouldering today. The project is expected to be completed early this week.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Mt Vernon Road Project Update: East Post to Hwy 13

1 Alert
May 12, 2017 7:09 AM

Mount Vernon Road Project Update:

The project was let on April 18, 2017 and the contract has been awarded to L.L. Pelling of North Liberty, IA for a cost of $4,423,753.78. The project is expected to last 8-12 weeks. The road will remain open at all times, but traffic will be controlled...

Read On...

Latest Update:

September 8, 2017 6:01 AM

Mount Vernon Road was reopened yesterday (7th) at 5:30 PM. The road is open to all traffic. However, Lincoln Heights Drive will remain closed just north of Mount Vernon Road. This closure is expected to last another 2 weeks.

Thank you for your cooperation. Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

N Center Point Rd: County Home to Center Point

1 Alert
June 1, 2017 1:37 PM

N Center Point Road Project Update

Culvert work and an 8" concrete overlay from County Home Road to the City of Center Point.

Latest Update:

September 22, 2017 3:57 PM

The contractor will stop paving near Lafayette Road this evening. They will not pave tomorrow and will resume paving on Monday (25th).

Please contact me with any questions.

Garret Reddish (garret-reddish@linnconunty.org)

Road Construction Updates

1 Alert
August 24, 2017 9:02 AM

Road Construction In Linn County

There are 5 projects that are staring soon. If interested, please go to http://www.linncounty.org/list.aspx and subscribe to the specific project update list.

1. Edgewood Road: Grading project between Tower Terrace Road and County Home Road.
2. N...

Read On...

Seal Coat: Various Locations in Linn County

0 Alerts
There are currently no alerts for this category.

Secrist Rd Project: Hwy 13 to Crystal Creek Rd

1 Alert
April 12, 2017 10:40 AM

Secrist Road Project Update

The project was let on January 18, 2017 and the contract has been awarded to Horsfield Construction, Inc. of Epworth, IA for a cost of $1,284,960.89. A schedule has not been submitted by the Contractor to date. As per the contract, the late start date...

Read On...

Latest Update:

August 2, 2017 11:08 AM

The contractor expects to open Secrist Road later this week (Thursday or Friday). There will be some follow up items that completed, but these will be done under traffic with flaggers.

Please contact me with any questions. Thanks for your cooperation.