Paving on Business 30 from the Lisbon city limits east to the dead end in Cedar County.

Facebook Twitter Email

Latest Update:

February 17, 2021 9:08 AM

The project was let on February 16, 2021 and the project was awarded to L.L. Pelling of North Liberty, Iowa for a cost of $577,784.06. As per the contract, the completion date for the project is October 2, 2021. This means the contractor may start the project at any time, but must finish before that date. Once started, the project will take approximately 4-6 weeks for completion. An exact start date has not been determined yet.

Garret Reddish (garret.reddish@linncounty.org)