Central City Road Bridge Replacement

◄ Back
November 13, 2019 12:45 PM

Central City Road Project Update

Bridge replacement on Central City Road over W Otter Creek is scheduled for 2020.

Facebook Twitter Email

Latest Update:

June 19, 2020 8:56 AM

The contractor is making good progress on the bridge. The contractor has completed the west abutment and both piers. The road remains closed and is on schedule to be opened in early August.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
June 2, 2020 9:02 AM

The contractor is currently removing the old bridge and plans to start driving pile later this week. The bridge should be open in late August.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

May 28, 2020 6:45 AM

The Central City Road bridge just west of Alice Road remains closed. Please contact me if you have any questions regarding the project or alternate routes.

Garret Reddish (garret.reddish@linncounty.org)