E Ave NW

◄ Back
January 21, 2021 9:07 AM

E Ave NW Update

A culvert and grading project on E Ave NW and Linn-Benton Road.

Facebook Twitter Email

Latest Update:

March 10, 2021 11:19 AM

Edit: The project was let on March 9, 2021 and was awarded to Rathje Construction of Marion, Iowa for a cost of $1,369,862.35. The project consists of roadtop widening, flattening foreslopes, and culvert replacements in preparation for a new seal coat surface. The contract specifies a late start date of June 1, 2021. This means the contractor must start the project before that date. Once started, the contractor will have 75 working days to complete the project. The contractor has not provided a start date at this time.