February 11, 2019 2:17 PM

East Post Road Project Update

The project was let on March 12, 2019 and the project was awarded to L.L. Pelling of North Liberty, Iowa for a cost of $327,646.13. The paving limits are from Fox Meadow Drive north to Cottage Grove Woods. As per the contract, the late start date for the project is August 12, 2019. This means the contractor may begin on or before that date. The contractor will be allowed 25 working days to complete the project. Once started, the project will take approximately 4-6 weeks for completion. An exact start date has not been determined yet.

Facebook Twitter Email

Latest Update:

October 7, 2019 10:03 AM

Thank you for subscribing to receive updates for the asphalt paving on East Post Road. To continually improve our customer satisfaction, we ask that you please fill out the survey at the link below.

Project Survey

Prior Updates

View All Updates
June 7, 2019 6:53 AM

The contractor finished the pavement markings yesterday and the project is now complete. Thank you for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)

June 4, 2019 9:18 AM

The pavement markings are scheduled to be painted on Thursday (6th). Once painted, the project will be complete.

Please contact me with any questions. Thank you for your cooperation!

Garret Reddish (garret.reddish@linncounty.org)