Jordan's Grove Road Bridge Replacement

◄ Back
February 11, 2019 2:11 PM

Jordan's Grove Road Project Update

The bridge replacement project on Jordans Grove Road was let on March 19, 2019 and the project was awarded to A.M. Cohron & Sons, Inc. of Atlantic, Iowa for a cost of $1,969,450.47. The bridge is over the Wapsipinicon River and a project schedule is not known at this time.

Facebook Twitter Email

Latest Update:

February 10, 2020 1:01 PM

Work continues to progress on the bridge replacement project. The contractor is placing concrete today for the footing of the middle pier. The project is on schedule to be completed by September.

Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

View All Updates
January 9, 2020 6:59 AM

The bridge replacement project has been underway for about 1 month and is still on schedule to finish by September. The contractor is currently removing the old bridge and is building temporary rock platforms in order to work in the river.

Please contact me if you have any questions.

Garret Reddish (garret.reddish@linncounty.org)

December 4, 2019 1:15 PM

The bridge replacement projected start on Monday December 2nd as planned. The project is expected to last 7-9 months and should be completed by September. There will not be a lot of project updates throughout construction. If you have questions please feel free to contact me. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)