Monticello Road Paving

◄ Back
February 11, 2019 2:24 PM

Monticello Road Project Update

The concrete paving project on Monticello Road was let on March 26, 2019 and the project was awarded to Horsfield Construction, Inc. of Epworth, Iowa for a cost of $1,156,513.58. The paving limits are from Prairieburg Road east to the Linn-Jones County line. A project schedule is not known at this time.

Facebook Twitter Email

Latest Update:

October 7, 2019 10:04 AM

Thank you for subscribing to receive updates for the concrete overlay project on Monticello Road. To continually improve customer satisfaction, we ask that you please fill out the survey at the link below.

Project Survey

Prior Updates

View All Updates
May 21, 2019 3:16 PM

The contractor is placing the rock shoulders this week. They plan to finish the road on Friday (24th) and switch over to Prairieburg Road. Monticello Road will be open to all traffic on Friday (24th). The pavement markings will not be completed yet. They will be painted when Prairieburg Road is completed and the two projects will be painted at the same time.

Please contact me with any questions. Thanks for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)

May 20, 2019 2:10 PM

The contractor is closing Nickel Plate Road today for intersection paving. It will remain closed for 2 days to allow concrete to mature. Monticello Road is open to local traffic.

Please contact me with any questions. Thank you for your cooperation.

Garret Reddish (garret.reddish@linncounty.org)