January 21, 2021 9:04 AM

Palo Paving Project Update

Concrete paving on Shellsburg Road, Blairs Ferry Road, and Palo Marsh Road.

Facebook Twitter Email

Latest Update:

May 19, 2021 7:49 AM

The contractor has pushed their start date back 1 month.  The concrete paving project near Palo is schedule to start the week of July 5 and be completed by August 6. The contractor will close Shellsburg Road and Blairs Ferry Road first, leaving Palo Marsh Road open initially. More details will be available as construction nears. Please contact me with any questions. Garret Reddish (garret.reddish@linncounty.org)

Prior Updates

April 9, 2021 1:57 PM

The concrete paving project near Palo is schedule to start appoximately on June 1 and be completed prior to August 6. The contractor will close Shellsburg Road and Blairs Ferry Road first, leaving Palo Marsh Road open initially.

More details will be available as construction nears.
Please contact me with any questions.

Garret Reddish (garret.reddish@linncounty.org)

January 26, 2021 12:37 PM

The project was let on January 26, 2021 and was awarded to Horsfield Construction, Inc. of Epworth, Iowa for a cost of $1,394,659.30. The contract specifies a completion date of August 6, 2021. This means the contractor must complete the project before that date. The contractor has not provided a start date at this time.